As per the New York City Department of Environmental Protection, the turbid discharge has been successfully halted and the Cannonsville Dam remains safe and uncompromised
The New York City Department of Environmental Protection (DEP)
announced that drinking water diversions and downstream releases from
Cannonsville Reservoir will be reduced to normal levels beginning Sunday
due to repair work that has successfully halted the turbid discharge
below Cannonsville Dam. The decision to resume normal operations at the
reservoir – made in consultation with engineers at the Federal Energy
Regulatory Commission (FERC) – also comes after weeks of testing and
around-the-clock monitoring that proved the dam is safe, stable and
uncompromised by the cloudy seepage that began three weeks ago.
Intensive monitoring at the site will continue as DEP resumes normal
operations at Cannonsville Reservoir. These efforts will include 24-hour
observations by on-site staff and surveillance cameras, daily
engineering inspections, and near real-time monitoring of turbidity and
safety instruments inside Cannonsville Dam. Although DEP is resuming
normal drinking water and release operations, reservoir storage will
likely continue to decline because the amount of water naturally flowing
into the reservoir is generally less than the amount of water released
to the river during summer.
On Saturday engineers began pumping
two additional relief wells, for a total of four, downstream of
Cannonsville Dam. These relief wells have successfully tapped into the
pressurized groundwater that was carrying sediment into the West Branch
Delaware River. By giving water from that aquifer a new path to flow,
the relief wells have ended the mobilization of sediment and the cloudy,
or turbid, water. Geotechnical engineers will turn their attention next
week to the original boreholes that entered the pressurized groundwater
and caused the condition below the dam. The process of permanently
sealing shut those boreholes with grout is expected to take
approximately one week.
After receiving approval from FERC on
Saturday afternoon, DEP began to shift toward normal operations early
Sunday morning. The drinking water diversion from Cannonsville Reservoir
will be reduced to zero, in favor of diverting more drinking water from
Pepacton and Neversink reservoirs. This will begin to balance the
storage in the Delaware Water Supply System, in accordance with normal
water supply operations. DEP will also begin to slowly reduce the amount
of water released into the West Branch Delaware River from 1,500 cubic
feet per second (cfs) to 500 cfs, the normal rate outlined in the
Flexible Flow Management Program. (Water is currently flowing into the
reservoir at a rate of approximately 300 cfs.) DEP has consulted with
fisheries biologists at the state Department of Environmental
Conservation (DEC) to develop the following schedule for reducing the
release over the next four days:
Aug. 2 – 1,125 cfs
Aug. 3 – 844 cfs
Aug. 4 – 633 cfs
Aug. 5 – 500 cfs
Reducing the rate of release will also significantly extend
the life of the cold water inside Cannonsville Reservoir, which is
important for the fisheries downstream and inside the reservoir itself.
There was approximately 25 billion gallons of cold water in the
reservoir as of Sunday morning.
DEP will continue to provide
updates on its Cannonsville Reservoir page and its watershed Facebook
page. The department also intends to schedule public information
meetings toward the end of August to discuss the repairs that were made
downstream of the dam. Local press outlets, elected officials, emergency
managers, and residents who attended DEP’s previous outreach meetings
will be notified directly when times, dates and locations are set.
Background
On July 15, DEP increased drinking water diversions and downstream
releases from Cannonsville Reservoir in response to an ongoing turbid
discharge from a rock embankment below Cannonsville Dam. While DEP, its
regulators, and consulting engineers did not believe the condition
represented a threat to dam safety, DEP began drawing down the reservoir
out of an abundance of caution to prioritize public safety while
repairs proceeded. Reducing reservoir storage at Cannonsville has not
posed a risk to the city’s water supply.
The turbid flow below
the dam was discovered when workers were drilling borings in preparation
for design and construction of a hydroelectric facility that is planned
to be built there. All drilling work ceased when the workers noticed
the flow of turbid water coming from a rock embankment near the release
chamber.
An investigation indicated that the drilling released
ground water under natural pressure, known as an artesian condition,
several dozen feet below surface level. This caused an upward flow of
water and sediment that was reaching the West Branch Delaware River.
Since then, DEP has continued intensive monitoring at the dam. These
include 24-hour monitoring by employees at the site, regular analysis of
dam-safety instrumentation, and testing of the turbid sediment to
identify and understand its origin. Federal, state, county and local
officials – including officials from New Jersey and Pennsylvania – have
been regularly updated since the condition at Cannonsville Dam was first
discovered.
Placed into service in 1964, Cannonsville
Reservoir was the last of New York City’s 19 reservoirs to be built.
Water diverted from Cannonsville Reservoir for drinking water enters the
West Delaware Tunnel and travels 44 miles to the upper end of Rondout
Reservoir. From there, it is carried in the 85-mile-long Delaware
Aqueduct. Water is released downstream from Cannonsville Reservoir under
the terms of the 1954 U.S. Supreme Court Decree, and a flow program,
known as the Flexible Flow Management Program, agreed upon by New York
City and the states of Delaware, New Jersey, New York and Pennsylvania.
All other reservoirs in the city’s Delaware System have continued to
meet their downstream release requirements under the Flexible Flow
Management Program while the condition at Cannonsville is repaired.